February 5, 2026
Project completed 8 months ahead of the original programme with £2 million saved on contents alone
A bespoke office development suffered a significant fire just one month before completion. The fire originated within the underfloor services void, causing widespread contamination throughout the building. Given the materials involved and the project’s critical timeline, rapid, specialist intervention was essential.
DF&A were appointed to independently assess the damage, ensure site safety, and manage the complex requirements of multiple stakeholders, enabling the project to continue with minimal delay.
The Challenge:
At the time of the incident, the end client was one month away from the project being completed so this had the potential to cause catastrophic delays to the project. The fire caused extensive contamination; through surface and air testing we found hazardous levels of chlorides and off-gassing of fire derived-VOC’s due to the combustion of PVC cabling and treated timber.
DF&A were tasked with:
Our Approach:
DF&A assessed the project, established a prioritised scope of works and provided clarity for all parties:
The Results:
Through our project management and practical, technical and scientific led approach, we were able to achieve fantastic results for the client, reducing the claims lifecycle and providing validation testing upon completion of the claim.
With the appointment of DF&A we swiftly moved the claim forward, minimising delays and allowing the end-client to occupy the building with the confidence that it had been effectively remediated and the root cause fully addressed.
If you would like to learn more about how we can help with complex and major claims resolution, please talk to us on 0800 8766626 or email us at info@davisfrench.co.uk
Company Registration No: 06378519 | Privacy Policy
© Davis French & Associates Ltd 2026
Website design and build by Grey Matter | web design sheffield